As summer draws to a close, the construction progress is stronger than ever.
On average there are 70-75 steel erectors, electricians, and concrete and mechanical experts working diligently to have Hangar B and Building 1 ready to open in January 2019.
Hangar B service pits have been installed,
The fuel farm is now onsite and going through the testing and certification stages. Over the next two months, the focus will be to complete the build out of Building 1, Hangar B, and the Paint Hangar. Major system installations in the near future include the RTO system in the Paint Hangar, air compressor system for the campus, and hangar door installation.