Duncan Aviation Provo Construction Update

Posted by Chad Doehring on Thu, Sep 13, 2018 @ 07:30 AM

As summer draws to a close, the construction progress is stronger than ever.IMG_0768

Hangar

On average there are 70-75 steel erectors, electricians, and concrete and mechanical experts working diligently to have Hangar B and Building 1 ready to open in January 2019.

Hangar B service pits have been installed, Fueland the entire hangar floor is now in. The Paint Hangar is on track to open in March 2019, and the structural steel is up and being closed in for Hangar C and Building 3 (opening June 2019). The structural steel is also being erected for Building 2 (opening in the first quarter of 2020).

The fuel farm is now onsite and going through the testing and certification stages. Over the next two months, the focus will be to complete the build out of Building 1, Hangar B, and the Paint Hangar. Major system installations in the near future include the RTO system in the Paint Hangar, air compressor system for the campus, and hangar door installation.FFFPicture2Picture5IMG_0771

IMG_0770Picture3The 14" thick ramp took 35,000 yards of concrete, and 6.5 million pounds of steel.Picture6Picture4

Tags: Duncan Aviation-Provo, Announcements, Community, engineering, construction